15 JUL

Summer Update

  • Published 2019-07-15

Otis Fiber Phase 4 installations have begun and should be complete by mid to late August. Strand and Fiber are being run in Phases 7, 8, 9. Installation of MST’s, splicing, and testing is ongoing in Phase 6 and the fiber hut at the center of town is due to go online the week of July 15. We are hopeful the project will be complete by the end of the year.

Read more
28 MAR

Spring 2019 Update

  • Published 2019-03-28

With spring comes an expected pick up in activity for Otis Fiber. Despite a few delays caused by mud we’re moving right along.

Read more
12 OCT

October Update

  • Published 2018-10-12

Things are going great for Otis Fiber. Wondering about the latest news?

Read more